HB 29

Texas HousePassed

Summary

HB 29, “Relating to water losses reported by certain municipally owned utilities to the Texas Water Development Board; authorizing administrative penalties”, was introduced in the House on Mar 13, 2025 by Rep. Stan Gerdes (R) with 4 co-sponsors. It last saw action on May 29, 2025: Effective immediately.


Record

Text

HB 29 has 4 co-sponsors and 7 roll calls.

hb29/enrolled.txt
H.B. No. 29
AN ACT
relating to water losses reported by certain municipally owned
utilities to the Texas Water Development Board; authorizing
administrative penalties.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1. Subchapter B, Chapter 16, Water Code, is amended
by adding Section 16.0122 to read as follows:
Sec. 16.0122. WATER AUDIT VALIDATION BY CERTAIN MUNICIPALLY
OWNED UTILITIES. (a) In this section, "municipally owned utility"
has the meaning assigned by Section 13.002.
(b) This section applies only to a municipally owned utility
that provides potable water through more than 150,000 service
connections.
(c) A municipally owned utility that has filed an annual
water audit under Section 16.0121 shall:
(1) not later than the 180th day after the date the
audit was filed, complete a validation of the audit to ensure the
utility accurately assessed potential inaccuracies in data used in
the audit; and
(2) not later than the first anniversary of the date
the audit was filed, develop and submit to the board a water loss
mitigation plan.
(d) Not later than December 31, 2030, and every 10 years
thereafter, a municipally owned utility that has filed an annual
water audit under Section 16.0121 shall:
(1) complete a more detailed validation of the
utility's most current water audit to:
(A) determine whether the implementation of
water leakage reduction strategies is appropriate; and
(B) investigate the accuracy of the utility's
billing data; and
(2) update the water loss mitigation plan developed by
the utility under Subsection (c)(2) accordingly.
(e) Each validation required under Subsection (c)(1) must
be performed by a person who has completed water audit validation
training and is certified to conduct the validation. The
validation:
(1) must follow board validation guidelines; and
(2) may not be conducted by a board staff member or the
person who submitted the water audit.
(f) Each water loss mitigation plan developed under
Subsection (c)(2), as updated under Subsection (d)(2), if
applicable, must be incorporated into the utility's most recent
water conservation plan required under Section 13.146 not later
than the first anniversary of the date the mitigation plan is
completed. As part of the utility's annual water conservation
report under Section 16.402(b), the utility shall report the
utility's progress in implementing the mitigation plan. The
mitigation plan must include:
(1) one-year, three-year, five-year, and ten-year
goals for water loss mitigation;
(2) descriptions of water loss mitigation projects or
programs designed to meet those goals;
(3) estimated financial savings from the
implementation of the projects or programs under Subdivision (2);
(4) estimated water savings from the implementation of
the projects or programs under Subdivision (2); and
(5) cost estimates for implementing each project or
program under Subdivision (2).
(g) If the utility must complete a validation under
Subsection (d)(1), the utility shall update the water loss
mitigation plan developed by the utility under Subsection (c)(2) to
revise the utility's one-year, three-year, five-year, and ten-year
goals.
(h) Each validation required under Subsection (d)(1) must
be performed by a person who is experienced in performing required
validation activities. The validation:
(1) must be based on the recommendations from the
utility's validation performed under Subsection (c)(1);
(2) must be completed in consultation with the person
who completed the validation under Subsection (c)(1);
(3) must be conducted in accordance with industry
standards; and
(4) may not be conducted by a board staff member or the
person who submitted the water audit.
(i) The commission shall assess against a municipally owned
utility an administrative penalty of $25,000 if the utility fails
to develop and submit to the board a water loss mitigation plan
required by Subsection (c)(2).
SECTION 2. This Act takes effect immediately if it receives
a vote of two-thirds of all the members elected to each house, as
provided by Section 39, Article III, Texas Constitution. If this
Act does not receive the vote necessary for immediate effect, this
Act takes effect September 1, 2025.
______________________________
______________________________
President of the Senate
Speaker of the House
I certify that H.B. No. 29 was passed by the House on April
25, 2025, by the following vote: Yeas 138, Nays 0, 2 present, not
voting; and that the House concurred in Senate amendments to H.B.
No. 29 on May 19, 2025, by the following vote: Yeas 129, Nays 0, 1
present, not voting.
______________________________
Chief Clerk of the House
I certify that H.B. No. 29 was passed by the Senate, with
amendments, on May 8, 2025, by the following vote: Yeas 31, Nays 0.
______________________________
Secretary of the Senate
APPROVED: __________________
Date
__________________
Governor

Relating to water losses reported by certain municipally owned utilities to the Texas Water Development Board; authorizing administrative penalties.

Sponsors

Rep. Stan Gerdes (R) sponsors HB 29, and 4 members have co-sponsored it.

Committees

HB 29 went before 2 committees: Natural Resources and Water, Agriculture, & Rural Affairs.

Natural Resources
Natural Resources
Referred to · Mar 14, 2025 · 183 Bills
Water, Agriculture, & Rural Affairs
Water, Agriculture, & Rural Affairs
Referred to · Apr 29, 2025

History

HB 29 has taken 58 actions since Mar 13, 2025, the latest on May 29, 2025.

ChamberAction
May 29, 2025
Signed by the Governor
May 29, 2025
Effective immediately
May 20, 2025
House
Signed in the House
May 20, 2025
Senate
House concurs in Senate amendment(s)-reported
May 20, 2025
Senate
Signed in the Senate

Votes

HB 29 went to 7 roll calls across both chambers, the latest on May 19, 2025 at 1290.

ChamberQuestion
Yea
Nay
May 19, 2025
House
House concurs in Senate amendment(s) RV#2993
129
0
May 8, 2025
Senate
Three day rule suspended
31
0
May 8, 2025
Senate
Read 3rd time
31
0
Apr 25, 2025
House
Read 3rd time RV#553
138
0
Apr 24, 2025
House
RV#498
136
3

Source: capitol.texas.gov · legiscan.com