H.R. 6633, the High-Capacity Grid Act, was introduced in the House on Dec 11, 2025 by Rep. Julie Fedorchak (R) with 4 co-sponsors. It last saw action on Jul 21, 2026: Ordered to be Reported (Amended) by the Yeas and Nays: 49 - 0.


Record

Text

H.R. 6633 has 4 co-sponsors.

hb6633/introduced-in-house.txt
119 HR 6633 IH: High-Capacity Grid Act
U.S. House of Representatives
2025-12-11
text/xml
EN
Pursuant to Title 17 Section 105 of the United States Code, this file is not subject to copyright protection and is in the public domain.
I 119th CONGRESS 1st Session H. R. 6633 IN THE HOUSE OF REPRESENTATIVES December 11, 2025 Mrs. Fedorchak introduced the following bill;
which was referred to the Committee on Energy
and Commerce A BILL
To establish a best-available transmission conductor standard for certain transmission projects under the Federal Power Act and to provide for presumptions regarding cost recovery for such conductors.
1.
Short title
This Act may be cited as the High-Capacity Grid Act .
2.
Best-available transmission conductor standard
Section 205 of the Federal Power Act ( 16 U.S.C. 824d ) is amended by adding at the end the following:
(h)
Best-Available transmission conductor standard
(1)
Definitions
In this subsection:
(A)
Best-available transmission conductor
The term best-available transmission conductor means a transmission conductor that, as determined by the Commission by rule under paragraph (5)—
(i)
provides the greatest feasible and commercially available energy-carrying capacity at a given voltage level;
(ii)
provides the highest feasible and commercially available electrical efficiency at that voltage level; and
(iii)
mitigates thermal sag at the maximum rated transmission-carrying capacity of the facility.
(B)
Covered project
The term covered project means—
(i)
the construction of a new transmission facility subject to the jurisdiction of the Commission under section 201(b); and
(ii)
any modification, upgrade, replacement, or reconductoring of an existing transmission line subject to such jurisdiction.
(2)
Presumption of prudence for best-available transmission conductors
In any filing seeking to recover the cost of a transmission conductor for a covered project, and in any proceeding to determine whether such cost may be recovered through rates, the Commission shall presume that the use of a best-available transmission conductor is a prudent practice and that the associated costs are just and reasonable.
(3)
Presumption against recovery of costs for non-best-available conductors
In any filing seeking to recover the cost of a transmission conductor for a covered project, and in any proceeding to determine whether such cost may be recovered through rates, the Commission shall presume that the use of a transmission conductor that is not a best-available transmission conductor is not prudent and that the associated costs are not just and reasonable.
(4)
Applicability
The requirements of this subsection apply only to public utilities and only with respect to covered projects that are subject to the jurisdiction of the Commission under section 201(b).
(5)
Rulemaking
Not later than 180 days after the date of enactment of this subsection, the Commission shall promulgate regulations to implement this subsection. In promulgating such regulations, the Commission shall—
(A)
establish a methodology for determining whether a transmission conductor is a best-available transmission conductor for purposes of this subsection;
(B)
ensure that such methodology is consistent with the criteria set forth in paragraph (1)(A); and
(C)
provide for periodic review and updating of the methodology to reflect improvements in technology, materials, and system performance.
.

Tracker

The tracker indicates the progress of this legislation as it moves through the legislative process.

  1. Introduced2025-12-11
  2. Passed House
  3. Passed Senate
  4. Conference
  5. To President
  6. Became Law

To establish a best-available transmission conductor standard for certain transmission projects under the Federal Power Act and to provide for presumptions regarding cost recovery for such conductors.

Sponsors

Rep. Julie Fedorchak (R) sponsors H.R. 6633, and 4 members have co-sponsored it.

Committees

H.R. 6633 went before 2 committees: Energy and Commerce and Energy Subcommittee.

Energy and Commerce
Energy and Commerce
Markup By · Jul 21, 2026 · 1,636 Bills
Energy Subcommittee
Energy Subcommittee
Reported by · Jun 24, 2026

Actions

H.R. 6633 has taken 8 actions since Dec 11, 2025, the latest on Jul 21, 2026.

ChamberAction
Jul 21, 2026
House
Ordered to be Reported (Amended) by the Yeas and Nays: 49 - 0.Energy and Commerce Committee
Jul 21, 2026
House
Committee Consideration and Mark-up Session HeldEnergy and Commerce Committee
Jul 20, 2026
House
Committee Consideration and Mark-up Session HeldEnergy and Commerce Committee
Jun 24, 2026
House
Subcommittee Consideration and Mark-up Session HeldEnergy Subcommittee
Jun 24, 2026
House
Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.Energy Subcommittee

Votes

H.R. 6633 has not gone to a roll call.

Titles

H.R. 6633 goes by 3 titles, 1 of them short titles.

  • High-Capacity Grid Act — Display Title
  • High-Capacity Grid Act — Short Title(s) as Introduced
  • To establish a best-available transmission conductor standard for certain transmission projects under the Federal Power Act and to provide for presumptions regarding cost recovery for such conductors. — Official Title as Introduced

Cost estimate

The Congressional Budget Office has filed 1 estimate for H.R. 6633, the latest on Sep 2, 2026.


Lobbying

32 clients hired 33 firms and 158 registered lobbyists who named H.R. 6633 in 55 quarterly filings, 2025 to 2026. Reported under the Lobbying Disclosure Act; a filing’s income covers everything its registrant worked that quarter, so the amounts below are the filings’, not this bill’s.

Filed under Energy/Nuclear, Taxation/Internal Revenue Code, Budget/Appropriations, Homeland Security, Environment/Superfund, Transportation, Telecommunications, Defense.

Clients

Who paid to be heard, by how many filings named the bill. The 20 that filed most often, of 32.

ClientBusinessStateFirmsFilingsReported
EDISON ELECTRIC INSTITUTEAssociation of US shareholder-owned electric companiesDistrict of Columbia25$100K
CORPORATE ENERGY BUYERS ASSOCIATIONDistrict of Columbia15
CTC GLOBAL CORPORATIONElectricity Transmission ManufacturerCalifornia13$130K
GOOGLE CLIENT SERVICES LLCDistrict of Columbia13
PORTLAND GENERAL ELECTRICOregon13
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATIONTrade association of electrical equipment manufacturersVirginia22$50K
AMERICAN ELECTRIC POWER COMPANY, INC. AND AFFILIATED CORPORATIONSDistrict of Columbia12
CMS ENERGY CORPDistrict of Columbia12
DUKE ENERGY CORPORATIONDistrict of Columbia12
HUNTSMAN INTERNATIONAL LLCTexas12
NATIONAL RURAL ELECTRIC COOPERATIVE ASSOCIATION (NRECA)Virginia12
PUGET SOUND ENERGYWashington12
SOUTHERN COMPANYDistrict of Columbia12
XCEL ENERGY INCDistrict of Columbia12
ONCOR ELECTRIC DELIVERYregulated electric distribution and transmission businessTexas11$60K
SOUTHWIRE COMPANYManufacturer of wire and cable used in the distribution and transmission of electricityGeorgia11$40K
AI SUPPLY CHAIN ALLIANCE (INFORMAL COALITION)AI-SCA is a coalition of companies building the physical systems that make AI possibleDistrict of Columbia11$30K
ELECTRICITY CUSTOMER ALLIANCECoalition advocating for reforms to electricity system.District of Columbia11$30K
ITC HOLDINGS CORPORATIONCorporation working to improve the electricity transmission grid to improve reliabilityMichigan11$20K
AMEREN SERVICESDistrict of Columbia11

Firms

Registrants who filed on the bill, by filings.

Lobbyists

Named on the filings that cite the bill. The 20 named most often, of 158.

Filings

The documents themselves, on the Senate’s Lobbying Disclosure site, largest reported first.

ClientRegistrantPeriodReportedDocument
GOOGLE CLIENT SERVICES LLCGOOGLE CLIENT SERVICES LLC2026 second_quarter$3.6M2nd Quarter - Report
PACIFIC GAS AND ELECTRIC COMPANYPACIFIC GAS AND ELECTRIC COMPANY2026 second_quarter$3.5M2nd Quarter - Report
GOOGLE CLIENT SERVICES LLCGOOGLE CLIENT SERVICES LLC2025 fourth_quarter$3.4M4th Quarter - Report
SOUTHERN COMPANYSOUTHERN COMPANY2026 second_quarter$3.2M2nd Quarter - Report
GOOGLE CLIENT SERVICES LLCGOOGLE CLIENT SERVICES LLC2026 first_quarter$2.9M1st Quarter - Report
AMERICAN PETROLEUM INSTITUTEAMERICAN PETROLEUM INSTITUTE2026 second_quarter$2.8M2nd Quarter - Report
EDISON ELECTRIC INSTITUTEEDISON ELECTRIC INSTITUTE2026 first_quarter$2.6M1st Quarter - Amendme…
EDISON ELECTRIC INSTITUTEEDISON ELECTRIC INSTITUTE2026 first_quarter$2.6M1st Quarter - Report
SOUTHERN COMPANYSOUTHERN COMPANY2026 first_quarter$2.5M1st Quarter - Report
DUKE ENERGY CORPORATIONDUKE ENERGY CORPORATION2026 second_quarter$2.3M2nd Quarter - Amendme…
DUKE ENERGY CORPORATIONDUKE ENERGY CORPORATION2026 second_quarter$2.3M2nd Quarter - Report
EDISON ELECTRIC INSTITUTEEDISON ELECTRIC INSTITUTE2026 second_quarter$1.7M2nd Quarter - Report
AMERICAN ELECTRIC POWER COMPANY, INC. AND AFFILIATED CORPORATIONSAMERICAN ELECTRIC POWER COMPANY, INC. AND AFFILIATED CORPORATIONS2026 first_quarter$1.2M1st Quarter - Report
DOW CHEMICAL COMPANY DBA DOWTHE DOW CHEMICAL COMPANY, DBA DOW2026 second_quarter$1.1M2nd Quarter - Report
NATIONAL RURAL ELECTRIC COOPERATIVE ASSOCIATION (NRECA)NATIONAL RURAL ELECTRIC COOPERATIVE ASSOCIATION (NRECA)2026 second_quarter$980K2nd Quarter - Report
XCEL ENERGY INCXCEL ENERGY, INC2026 first_quarter$960K1st Quarter - Report
NATIONAL RURAL ELECTRIC COOPERATIVE ASSOCIATION (NRECA)NATIONAL RURAL ELECTRIC COOPERATIVE ASSOCIATION (NRECA)2026 first_quarter$850K1st Quarter - Report
INFORMATION TECHNOLOGY INDUSTRY COUNCILINFORMATION TECHNOLOGY INDUSTRY COUNCIL2026 second_quarter$720K2nd Quarter - Report
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATIONNATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION2026 second_quarter$650K2nd Quarter - Report
ENTERGY SERVICES LLCENTERGY SERVICES, LLC2026 second_quarter$610K2nd Quarter - Report

Classification

The Congressional Research Service files H.R. 6633 under Energy, one of its 31 policy areas, and gives it 6 legislative subjects.

CRS Subjects

CRS assigns every bill one policy area from its 31; H.R. 6633’s is Energy.

hr6633/policy-areas.txt
EnergyAgriculture and FoodAnimalsArmed Forces and National SecurityArts, Culture, ReligionCivil Rights and Liberties, Minority IssuesCommerceCongressCrime and Law EnforcementEconomics and Public FinanceEducationEmergency ManagementEnvironmental ProtectionFamiliesFinance and Financial SectorForeign Trade and International FinanceGovernment Operations and PoliticsHealthHousing and Community DevelopmentImmigrationInternational AffairsLabor and EmploymentLawNative AmericansPublic Lands and Natural ResourcesScience, Technology, CommunicationsSocial WelfareSports and RecreationTaxationTransportation and Public WorksWater Resources Development

Legislative Subjects

H.R. 6633 carries 6 of CRS’s legislative subjects, from Advisory bodies to Technology assessment.

hr6633/subjects.txt
Advisory bodiesElectric power generation and transmissionEnergy efficiency and conservationEnergy pricesEnergy storage, supplies, demandTechnology assessment

Constitutional authority

The clause the sponsor cites as Congress’s power to enact H.R. 6633, as entered in the Congressional Record.

[Congressional Record Volume 171, Number 209 (Thursday, December 11, 2025)][House]From the Congressional Record Online through the Government Publishing Office [www.gpo.gov]By Ms. FEDORCHAK:H.R. 6633.Congress has the power to enact this legislation pursuantto the following:Clause 3 of Section 8 of Article I of the Constitution ofthe United States.[Page H5810]