HB 562

Virginia HousePassed

Summary

HB 562, “Electric cooperatives; authorized to establish and implement a virtual power plant program”, was introduced in the House on Jan 13, 2026 by Rep. David Reid (D). It last saw action on Mar 31, 2026: Acts of Assembly Chapter text (CHAP0044).


Record

Text

HB 562 has 7 roll calls.

hb562/chaptered.txt
An Act to amend the Code of Virginia by adding a section numbered 56-585.1:17, relating to electric cooperatives; virtual power plant program.
Be it enacted by the General Assembly of Virginia:
1. That the Code of Virginia is amended by adding a section numbered 56-585.1:17 as follows:
§ 56-585.1:17. Virtual power plant program; electric cooperatives.
A. As used in this section:
"Aggregator" means an individual or entity, other than the electric cooperative, that enrolls customers in a virtual power plant program and coordinates the operation of enrolled energy resources. An aggregator shall not be considered an electric utility by virtue of participating in a virtual power plant program but shall, as part of its agreement with a participating cooperative, receive participating customer and grid data from the cooperative to participate in such program.
"Distributed energy resource" means a resource of up to five megawatts that is located on the customer's premises or is interconnected with the distribution system and produces or stores electricity or modifies the timing or amount of a customer's electricity consumption.
"Electric cooperative" or "cooperative" means a utility formed under or subject to Article 1 of Chapter 9.1 (§ 56-231.15 et seq.).
"Eligible technology" means a distributed energy resource that meets the requirements for participation in a virtual power plant program and does not emit carbon dioxide as a byproduct of combusting fuel or manufacturing fuel for combustion to generate electricity.
"Grid event" means a grid condition for which the electric cooperative schedules or remotely dispatches enrolled devices to respond.
"Grid service" means a capacity, energy, or ancillary service that supports grid operations.
"Historically economically disadvantaged community" has the same meaning as provided in § 56-576.
"Virtual power plant" means an aggregation of distributed energy resources, enrolled either directly with an electric cooperative or indirectly through an aggregator, that are operated in coordination to provide one or more grid services.
B. On or after January 1, 2027, notwithstanding any other provision of law, an electric cooperative may, without Commission approval, upon an affirmative resolution of its board of directors and without the requirement of any filing other than as required by this section, propose, establish, and implement a virtual power plant program, provided that such program adheres to the requirements of this section. This regulated, tariffed program shall be reviewable by the Commission at the electric cooperative's next general rate proceeding. An electric cooperative shall recover the costs of such virtual power plant program through a new rate schedule established by this section or otherwise through its rates. An electric cooperative establishing such a program shall file a copy of any such new rate schedule with the Commission for informational purposes.
C. Any such virtual power plant program shall consist of aggregations of distributed energy resources. An electric cooperative may utilize any existing or proposed distributed energy programs to further the development of virtual power plants in the Commonwealth. An electric cooperative that establishes a virtual power plant program shall demonstrate in the informational filing required by subsection B that the cooperative has evaluated funding opportunities from the federal government. In furthering the goals of such program, the electric cooperative may offer incentives to residential customers to purchase battery storage devices, and if the cooperative does offer such incentives, it shall conduct a competitive solicitation for the provision of such battery storage devices that is open to cooperative-owned and non-cooperative-owned resources.
D. In conducting such virtual power plant program, the electric cooperative shall evaluate methods to holistically optimize demand, including (i) a stakeholder process to receive feedback on virtual power plant program design; (ii) a review of reasonable enrollment and performance incentives for participating customers; (iii) potential incentives for the purchase of a battery storage device, including increased incentives for customers in historically economically disadvantaged communities; (iv) operational parameters for grid services, including the annual maximum number of grid events, the maximum duration of such grid events, and conditions under which a participating customer may opt out of a grid event; (v) reasonable mechanisms to disenroll customers for nonperformance; and (vi) preliminary development of a virtual power plant program tariff that is designed to (a) allow customers with technologies, including battery storage, non-battery storage, smart thermostat, or managed electric vehicle charging technologies, to enroll their eligible technologies in such program; (b) provide a mechanism to incorporate existing programs, including smart thermostat demand response programs, electric vehicle charging programs, and battery storage programs, into such tariff; (c) specify compensable grid services for each eligible technology, including peak demand reduction, voltage support, and emergency services; and (d) specify pay-for-performance compensation mechanisms for such grid services.

Electric utilities; virtual power plant program; electric cooperatives. Authorizes electric cooperatives to establish and implement a virtual power plant program. The bill defines a virtual power plant as an aggregation of distributed energy resources, enrolled either directly with an electric cooperative or indirectly through an aggregator, that are operated in coordination to provide one or more grid services. Under the bill, an electric cooperative may offer incentives to residential customers to purchase battery storage devices and is required to evaluate various methods to optimize demand. This bill is identical to SB 487.

Sponsors

Rep. David Reid (D) sponsors HB 562 alone.

Committees

HB 562 went before 3 committees: Labor and Commerce, Labor and Commerce: Subcommittee #3 and Commerce and Labor.

Labor and Commerce
Labor and Commerce
Referred to · Jan 13, 2026 · 50 Bills
Labor and Commerce: Subcommittee #3
Labor and Commerce: Subcommittee #3
Referred to · Jan 20, 2026
Commerce and Labor
Commerce and Labor
Referred to · Feb 3, 2026 · 2 Bills

History

HB 562 has taken 32 actions since Jan 13, 2026, the latest on Mar 31, 2026.

ChamberAction
Mar 31, 2026
Approved by Governor-Chapter 44 (effective 7/1/2026)
Mar 31, 2026
Acts of Assembly Chapter text (CHAP0044)
Mar 12, 2026
House
Fiscal Impact Statement from State Corporation Commission (HB562)
Mar 10, 2026
House
Enrolled Bill communicated to Governor on March 10, 2026
Mar 10, 2026
Governor's Action Deadline 11:59 p.m., April 13, 2026

Votes

HB 562 went to 7 roll calls across both chambers, the latest on Mar 2, 2026 at 981.

ChamberQuestion
Yea
Nay
Mar 2, 2026
House
Senate substitute agreed to by House (98-Y 1-N 0-A)
98
1
Feb 26, 2026
Senate
Passed Senate with substitute (39-Y 1-N 0-A)
39
1
Feb 25, 2026
Senate
Constitutional reading dispensed Block Vote (on 2nd reading) (40-Y 0-N 0-A)
40
0
Feb 23, 2026
Senate
Reported from Commerce and Labor (14-Y 0-N)
14
0
Feb 2, 2026
House
Read third time and passed House (99-Y 0-N 0-A)
99
0

Source: lis.virginia.gov · legiscan.com