S 2580, which sets timelines for Tiverton's new construction, including one year for final approval, two (2) years for building permits, and temporary inclusion of units in the town's count until completion or three (3) years, whichever comes first, was introduced in the Senate on Feb 13, 2026 by Sen. Walter Felag (D) with 1 co-sponsor. It was referred to Housing and Municipal Government, and last saw action on May 12, 2026: Committee recommended measure be held for further study.


Record

Text

S 2580 has 1 co-sponsor and 1 roll call.

s2580/introduced.txt
2026 -- S 2580
========
LC005241
========
STATE OF RHODE ISLAND
IN GENERAL ASSEMBLY
JANUARY SESSION, A.D. 2026
____________
AN ACT
RELATING TO TOWNS AND CITIES -- TIVERTON'S NEW CONSTRUCTION PROJECTS
ACT
Introduced By: Senators Felag, and DiPalma
Date Introduced: February 13, 2026
Referred To: Senate Housing & Municipal Government
(by request)
It is enacted by the General Assembly as follows:
SECTION 1. Title 45 of the General Laws entitled "TOWNS AND CITIES" is hereby
amended by adding thereto the following chapter:
CHAPTER 53.1
TIVERTON'S NEW CONSTRUCTION PROJECTS ACT
45-53.1-1. Title.
This chapter shall be known and may be cited as the "Tiverton's New Construction Projects
Act."
45-53.1-2. Definitions.
For the purposes of this chapter, the following words and terms shall have the following
meanings:
(1) "Bonus units" means additional residential units approved by the town of Tiverton as
part of a development project in accordance with the town's zoning and development policies.
(2) "Building permit" means a permit issued by the town of Tiverton granting authorization
for the commencement of construction on a project.
(3) "Certificate of occupancy" means a certificate issued by the town of Tiverton
confirming that a building has been completed in compliance with all building codes and is safe
for occupancy.
(4) "Final approval" means the final authorization given by the town of Tiverton following
successful completion of all necessary review and approval processes for a development project.
(5) "Preliminary approval" means the initial approval granted to a development project
after review and recommendation by the appropriate municipal authority.
45-53.1-3. Timelines for approval and permitting.
(a) In the town of Tiverton, the period between the granting of preliminary approval and
the granting of final approval for a development project shall not exceed one year.
(b) In the town of Tiverton, the period between the granting of final approval and the
issuance of a building permit shall not exceed two (2) years.
(c) In the town of Tiverton, if the applicant does not request a building permit within the
two (2) year period following final approval, the application and vesting shall be considered void.
The development process shall need to be restarted, and the applicant will need to resubmit a new
application for review and approval.
45-53.1-4. Temporary addition of units to town's total unit count.
(a) In the town of Tiverton, once an applicant requests a building permit, the number of
units approved for the development, including any bonus units, shall be temporarily added to the
total unit count. This count shall be included in the town of Tiverton's current housing inventory.
(b) The units, including bonus units, shall be permanently added to the town of Tiverton's
unit count upon the issuance of a certificate of occupancy for the development or three (3) years
from the date of the request for a building permit, whichever occurs first.
(c) The town of Tiverton shall be allowed to count the units, including bonus units, against
other new developments while the construction is ongoing. This allowance shall ensure that the
town of Tiverton remains in compliance with its housing and development goals, while still
providing flexibility to the applicant during the construction phase.
SECTION 2. This act shall take effect upon passage.
========
LC005241
========
LC005241 - Page 2 of 3
EXPLANATION
BY THE LEGISLATIVE COUNCIL
OF
AN ACT
RELATING TO TOWNS AND CITIES -- TIVERTON'S NEW CONSTRUCTION PROJECTS
ACT
***
This act would set timelines for Tiverton's new construction, including one year for final
approval, two (2) years for building permits, and temporary inclusion of units in the town's count
until completion or three (3) years, from the requested date of the building permit whichever comes
first.
This act would take effect upon passage.
========
LC005241
========
LC005241 - Page 3 of 3

TOWNS AND CITIES -- TIVERTON'S NEW CONSTRUCTION PROJECTS ACT - Sets timelines for Tiverton's new construction, including one year for final approval, two (2) years for building permits, and temporary inclusion of units in the town's count until completion or three (3) years, whichever comes first.

Sponsors

Sen. Walter Felag (D) sponsors S 2580, and 1 member has co-sponsored it.

Committees

S 2580 went before 1 committee: Housing and Municipal Government.

Housing and Municipal Government
Housing and Municipal Government
Referred to · Feb 13, 2026

History

S 2580 has taken 3 actions since Feb 13, 2026, the latest on May 12, 2026.

ChamberAction
May 12, 2026
Senate
Committee recommended measure be held for further study
May 8, 2026
Senate
Scheduled for hearing and/or consideration (05/12/2026)
Feb 13, 2026
Senate
Introduced, referred to Senate Housing and Municipal Government

Votes

S 2580 went to 1 roll call in the Senate, the latest on May 12, 2026 at 60.

ChamberQuestion
Yea
Nay
May 12, 2026
Senate
Senate Committee on Housing & Municipal Government: Be held for further study
6
0

Source: status.rilegislature.gov · legiscan.com