S. 4806, the POWER Up Act, was introduced in the Senate on Jun 17, 2026 by Sen. Cynthia Lummis (R). It was referred to Energy And Natural Resources, and last saw action on Jun 17, 2026: Read twice and referred to the Committee on Energy and Natural Resources.


Record

Text

S. 4806 has no co-sponsors and has not gone to a roll call.

sb4806/introduced-in-senate.txt
119 S4806 IS: Promoting Oversight of Wholesale Energy Reliability Act
U.S. Senate
2026-06-17
text/xml
EN
Pursuant to Title 17 Section 105 of the United States Code, this file is not subject to copyright protection and is in the public domain.
II 119th CONGRESS 2d Session S. 4806 IN THE SENATE OF THE UNITED STATES June 17, 2026 Ms. Lummis introduced the following bill; which was read twice and referred to the Committee on Energy and Natural Resources A BILL
To clarify that the interconnection of large load facilities directly to facilities used for the transmission of electric energy in interstate commerce is a matter within the jurisdiction of the Federal Energy Regulatory Commission.
1.
Short title
This Act may be cited as the Promoting Oversight of Wholesale Energy Reliability Act or the POWER Up Act .
2.
Clarification of Federal jurisdiction over large load interconnection
Section 201 of the Federal Power Act ( 16 U.S.C. 824 ) is amended by adding at the end the following:
(h)
Jurisdiction over large load interconnection
(1)
Definitions
In this subsection:
(A)
Commission
The term Commission means the Federal Energy Regulatory Commission.
(B)
Large load facility
(i)
In general
The term large load facility means any facility, or group of facilities described in clause (ii), the projected aggregate peak electricity demand of which is 100 megawatts or greater, subject to clause (iii).
(ii)
Group of facilities described
A group of facilities referred to in clause (i) is a group of facilities—
(I)
under common ownership or control; and
(II)
located at—
(aa)
a single site; or
(bb)
contiguous sites.
(iii)
Adjustment
The Commission may, by rule, adjust the projected aggregate peak electricity demand at which a facility, or a group of facilities described in clause (ii), will be considered to be a large load facility, as the Commission determines to be necessary to ensure—
(I)
the reliability of the bulk-power system (as defined in section 215(a)); and
(II)
the provision of just, reasonable, and not unduly discriminatory or preferential transmission service.
(2)
Jurisdiction over interconnection
(A)
In general
The Commission shall have jurisdiction over the interconnection of any large load facility to 1 or more facilities used for the transmission of electric energy in interstate commerce.
(B)
Treatment
The interconnection of a large load facility as described in subparagraph (A) shall be—
(i)
subject to the requirements of this section, section 205, and section 206; and
(ii)
considered to be a component of open access transmission service.
(3)
Rulemaking
Not later than 18 months after the date of enactment of this subsection, the Commission shall issue a final rule establishing—
(A)
standardized procedures and agreements for the interconnection of large load facilities, including procedures for hybrid facilities that combine large load and generation at a single point of interconnection; and
(B)
a test for transmission facilities to aid in the interconnection of large load facilities and transmission facilities, including transmission lines.
(4)
Preservation of State authority
Nothing in this subsection affects the authority of any State or local government over—
(A)
the siting, permitting, or construction of any facility;
(B)
retail electric service or rates;
(C)
facilities used in the local distribution of electric energy; or
(D)
the generation of electric energy.
.

Tracker

The tracker indicates the progress of this legislation as it moves through the legislative process.

  1. Introduced2026-06-17
  2. Passed Senate
  3. Passed House
  4. Conference
  5. To President
  6. Became Law

A bill to clarify that the interconnection of large load facilities directly to facilities used for the transmission of electric energy in interstate commerce is a matter within the jurisdiction of the Federal Energy Regulatory Commission.

Sponsors

Sen. Cynthia Lummis (R) sponsors S. 4806 alone.

Committees

S. 4806 went before 1 committee: Energy and Natural Resources.

Energy and Natural Resources
Energy and Natural Resources
Referred To · Jun 17, 2026 · 314 Bills

Actions

S. 4806 has taken 2 actions since Jun 17, 2026.

ChamberAction
Jun 17, 2026
Senate
Read twice and referred to the Committee on Energy and Natural Resources.Energy and Natural Resources Committee
Jun 17, 2026
Introduced in Senate

Votes

S. 4806 has not gone to a roll call.

Titles

S. 4806 goes by 4 titles, 2 of them short titles.

  • POWER Up Act — Display Title
  • POWER Up Act — Short Title(s) as Introduced
  • Promoting Oversight of Wholesale Energy Reliability Act — Short Title(s) as Introduced
  • A bill to clarify that the interconnection of large load facilities directly to facilities used for the transmission of electric energy in interstate commerce is a matter within the jurisdiction of the Federal Energy Regulatory Commission. — Official Title as Introduced

Classification

The Congressional Research Service files S. 4806 under Energy, one of its 31 policy areas.

CRS Subjects

CRS assigns every bill one policy area from its 31; S. 4806’s is Energy.

s4806/policy-areas.txt
EnergyAgriculture and FoodAnimalsArmed Forces and National SecurityArts, Culture, ReligionCivil Rights and Liberties, Minority IssuesCommerceCongressCrime and Law EnforcementEconomics and Public FinanceEducationEmergency ManagementEnvironmental ProtectionFamiliesFinance and Financial SectorForeign Trade and International FinanceGovernment Operations and PoliticsHealthHousing and Community DevelopmentImmigrationInternational AffairsLabor and EmploymentLawNative AmericansPublic Lands and Natural ResourcesScience, Technology, CommunicationsSocial WelfareSports and RecreationTaxationTransportation and Public WorksWater Resources Development

Source: congress.gov · legiscan.com